Project Update April 11, 2023: The removal of slabs, footings, and other materials from the site is almost complete.
Project Update March 20, 2023: Structural demolition is complete and the removal of slabs and footings is progressing.
Project Update February 20, 2023: Structural demolition continues.
Project Update February 14, 2023: Structural demolition continues at the site.
Project Update February 8, 2023: Project Update - Sharp Facility Demolition: The structural demolition of the facility has started. The project will be completed in March 2023, making way for parking improvements at Sharp Stadium.